  • UPDF Seeks Extra UGX 526M to finish Construction works at Rubaare HC IV.
  • NEWS

UPDF Seeks Extra UGX 526M to finish Construction works at Rubaare HC IV.

Hamlet Arinda 1 year ago 3 minutes read
IMG_20250114_174503_068

NTUNGAMO: The UPDF Western region Engineering bridged Projects Manager Lt. Richard Isingoma has requested an extra fund release of Shs 526 Million to complete the construction of Rubare HC IV maternity ward.

Thank you for reading this post, don't forget to subscribe!

Isingoma made the revelation during the site inspection meeting with Ntungamo district stakeholders on Tuesday this week at the site ground in Rubaare town council.

He confirmed to the stakeholders that they first received an initial sum of UGX 400 Million from the Ministry of health to work on three scopes, which include the sub structure, concrete flames and roofing at the facility which is a presidential Pledge.

However, Isingoma said that due to money constraints, they ended up diverting the money for roofing to cater for the external and internal walls to balance the building’s ground support, because the column to column distance was larger than they had anticipated.

“”We had to use funds released for roofing to construct inner and outside walls. This was the only choice because the column to column distance is too far and can’t allow the isolated beams without some supporting walls. If at all we couldn’t understand this, there would have occurred some surging so, the remaining balance will start on the roofing.” Said Richard Isingoma.

Isingoma added that Ntungamo district has gotten more release on two sites and in Rubaare the Ministry added UGX 300 Million to top up on the first release of UGX 400 Million to add up to UGX 700 Million and now the project costing approximately UGX 1.26 billions.

“Despite the Ministry of health releasing the addition of UGX 300 Million as a top up on the first release, we ask for an extra over UGX 500 Million to finish the structure.” Insigoma added.

He also underscored the challenges at the site like poor roads connecting to sites which lead them to offload the materials in far distance to the site, which also incur unexpected costs to transport materials thus delaying the work.

The Deputy Resident District Commissioner Mr Daniel Twakira commended the government for the initiatives in the health sector and further called for vigilant among the public over criminals that delay the project.

“This initiative will be commendable for a long way boosting health care in the district. So I want to encourage you to be vigilant in monitoring this project as soon heartless people are planning to tamper with the construction.” Said Daniel Twakira.

The Rubaare HC IV Chairman Management Committee Mr Fred Muhweezi re-echoed the sentiments of RDC that the initiative will boost the service delivery at the facility and hailed the government under stewardship of President Museveni for the keen interest in the health sector.

The project is contracted by the UPDF Engineering Brigade that ring fenced all government projects.

About the Author

Hamlet Arinda

Administrator

Visit Website View All Posts

Post navigation

Previous: Rubanda Authorities Commission School Infrastructure Projects worth Hundreds of Million Shillings
Next: CRIME INTELLIGENCE. Kasese Police nets 34 including Notorious Gang Members

Related Stories

images (17)
  • NEWS
  • SECURITY

LC Chairpersons Cautioned on Fraudulent Use of Official Stamps

Tugume Muzafaru 60 minutes ago
GridArt_20260624_215212693
  • NEWS
  • POLITICS

Museveni Shuffles Foreign Affairs Ministry: Haruna Kasolo In, Ayebare Out

Hamlet Arinda 7 hours ago
1782312564910
  • NEWS

Chief Justice Orders Judicial Officers to Embrace Mediation to Tackle Case Backlog

Admin 11 hours ago

Featured News

  • LC Chairpersons Cautioned on Fraudulent Use of Official Stamps June 25, 2026
  • Museveni Shuffles Foreign Affairs Ministry: Haruna Kasolo In, Ayebare Out June 24, 2026
  • Chief Justice Orders Judicial Officers to Embrace Mediation to Tackle Case Backlog June 24, 2026
  • Uganda Prisons Service Elevates 258 Senior Officers in Major Promotion Exercise June 24, 2026
  • Driver Caught with 13 Bullets, Military Gear in Police Operation June 24, 2026
  • Japan Grants $500,000 to Boost Uganda’s Ebola Response Efforts June 24, 2026
  • Munoz Strike Sends Colombia Into World Cup Knockout Stages June 24, 2026
  • Bribery Claims Rock LDC Court Open Day as Public Confronts Police Commander June 23, 2026

About AF themes

You May Have Missed

images (17)
  • NEWS
  • SECURITY

LC Chairpersons Cautioned on Fraudulent Use of Official Stamps

Tugume Muzafaru 60 minutes ago
GridArt_20260624_215212693
  • NEWS
  • POLITICS

Museveni Shuffles Foreign Affairs Ministry: Haruna Kasolo In, Ayebare Out

Hamlet Arinda 7 hours ago
1782312564910
  • NEWS

Chief Justice Orders Judicial Officers to Embrace Mediation to Tackle Case Backlog

Admin 11 hours ago
1782297151470_1
  • NEWS
  • SECURITY

Uganda Prisons Service Elevates 258 Senior Officers in Major Promotion Exercise

Hamlet Arinda 15 hours ago
  • INTERNATIONAL
  • NATIONAL
  • SPORTS
  • HEALTH
  • LIFESTYLE
  • POLITICS
  • NEWS
  • CUSTOMS
  • #8459 (no title)
  • #8450 (no title)
  • #8442 (no title)
  • Blog
  • CoverNews
  • CULTURAL
  • CUSTOMS
  • CUSTOMS & SOCIAL BEHAVIOUR
  • Environment
  • Health
  • HEALTH
  • Home
  • Home
  • INTERNATIONAL
  • LIFESTYLE
  • NATIONAL
  • NEWS
  • Newsever
  • Politics
  • POLITICS
  • Sample Page
  • SPORTS
  • Sports
  • The News
Copyright © 2026 All rights reserved. | ReviewNews by AF themes.